Task 5 :Project Cost Planning

mONEY...MOneY
                                              
           IMPORTANCE OF COST CONTROL
  v  Cost is one of the project objectives
  v  Unless cost is controlled, project objectives can be jeopardized
  v  Cost, time and quality are interlinked.  Cost control is most critical
  v  Most poorly managed projects have cost overrun

     3W AND 1H IN COST CONTROL 
  v  Who controls cost?
  v  When to control cost?
  v  Where to control cost?
  v  How to control cost?


          COST COLLECTION
              v Labour
        v Material
        v    Cost codes
  
          CALCULATION VARIANCES
                 ü  Schedule Variances (SV)
·         SV = BCWP – BCWS
·         Positive SV means work is ahead of schedule

ü  Cost Variances (CV)
·         CV = BCWP – ACWP
·         Negative CV means overspending
  
          PERFORMANCE INDICES
   ü  Cost performance index (CPI)
·         CPI= BCWP/ACWP

   ü  Schedule Performance Index (SPI)
·         SPI = BCWP/BCWS